Vote proposal: Technical items still to be done

Tomas Mraz tmraz at redhat.com
Thu Oct 8 09:51:48 UTC 2020


On Thu, 2020-10-08 at 09:47 +0100, Matt Caswell wrote:
> 
> On 07/10/2020 19:07, Kurt Roeckx wrote:
> > On Wed, Oct 07, 2020 at 12:35:28PM +0100, Matt Caswell wrote:
> > > The following items are required prerequisites for the first beta
> > > release:
> > [...]
> > > * Address 3.0beta1 milestones.
> > 
> > So we now have a list here, with the last item pointing to a
> > different list. I suggest that we only have 1 list, and that we
> > make github issues for anything that doesn't have an issue yet,
> > and it to the milestone. It would at least be easier to track the
> > progress.
> 
> I agree, although its bit of a chicken-and-egg problem. I'd suggest
> voting on the list as is, and then if the vote passes converting all
> of
> those things into issues.

+1

> > We also talked about freezing the milestone at some point. We
> > intend to go over the 3.0.0 milestone PRs/issues, and see if any of
> > those need to be moved to the 3.0.0 beta1 milestone. I assume that
> > if we have done that, that we'll freeze it. We can then try to
> > estimate how long it will take before beta1.
> 
> Yes.
> 
> Matt
> 
-- 
Tomáš Mráz
No matter how far down the wrong road you've gone, turn back.
                                              Turkish proverb
[You'll know whether the road is wrong if you carefully listen to your
conscience.]




More information about the openssl-project mailing list